Introduction

We are going to break down the framing into 3 framing modules that will be assembled on the ground in parallel with other construction processes.

This is the how-to for the first modules of the 1st floor. Starting from the south, they are labeled 1-10 with an "a" and "b" distinction referencing their location on either west or east respectively.

  1. Gather Material for Mod. 3a+b 4:2x4x6'
    • Gather Material for Mod. 3a+b

    • 4:2x4x6'

    • 4:2x4x8'

    • 2 Sheets 1/2"x4'x8' Plywood (1 sheet for Mod.3a, 1 for Mod.3b)

    • 2 Sheets 3/4"x4'x8' OSB (1 sheet for Mod.3a, 1 for Mod.3b)

    • ~30: 3-1/8" Construction Screw

    • ~64: 1-5/8" coated deck screw