| + | [* black] Pour the concrete into the forms. Then, place your caps for the door recesses into place and level the top of the concrete using a board to screed off the excess. |
|---|---|
| + | [* black] The image shows what you will have created once the concrete is poured into the forms. |
| + | [* black] You may have chosen to place additional stub-outs of rebar as shown in the second image or in other places. If you do, the holes for these pieces of rebar will be located like the other stub-outs: 4" apart from each other and 4" in from each edge of the foundation formwork. |