Changes to Step #5
Edit by Dozuki System —
Edit approved by Dozuki System
- Before
- After
- Unchanged
Step Lines
| + | [title] Tack Roof, Inner Rails |
|---|---|
| + | [* black] Grind off the welds for the back and side pieces so that the entire drawer is flush. |
| + | [* black] Flip the drawer over and tack the sides from the top. |
| + | [* black] Place the roof and inner rails in their respective places. See Diagram. |
| + | [* icon_caution] Insure inner rails are perfectly parallel (varying no more than a 16th of an inch) and square throughout the entire length. |
| + | [* black] Tack them in multiple places except where they are touching the table. |
Image 1
No previous image
Added
Image 2
No previous image
Added
Image 3
No previous image
Added