We are going to break down the framing into 3 framing modules that will be assembled on the ground in parallel with other construction processes.
This is the how-to for the first modules of the 1st floor. Starting from the south, they are labeled 1-10 with an "a" and "b" distinction referencing their location on either west or east respectively.
Time Required Min
1 minute
Time Required Max
1 minute
Difficulty
Moderate
Author
Public
No
Summary
This guide will explain how to construct the 2x4 modules of the walls that sit atop the masonry and provide the 17 degree slope of the roof.