Introduction
We are going to break down the framing into 11 framing modules that will be assembled on the ground in parallel with other construction processes.
This is the how-to for the modules of the 2nd floor. Starting from the south, they are labeled 4-9 with an "a" and "b" distinction referencing their location on either west or east respectively.
-
-
Gather materials for Mod. 7a+b
-
4:2x4x6'
-
2:2x4x8'
-
2:2x4x10'
-
2:1/2"x4'x8' Plywood
-
2:3/4"x4'x8' OSB
-
~50: 3-1/8" construction screw
-
~50: 1-5/8" coated deck screw
-