  1. Lay out materials for outer frame from http://labs.nortd.com/lasersaur/bom-subs...
  2. Preassemble corner pieces, 2 mirror images Use 3 double brackets. Until the very end, leave all connections loose.
    • Preassemble corner pieces, 2 mirror images Use 3 double brackets. Until the very end, leave all connections loose.

  3. Build second corner bracket for front of frame
    • Build second corner bracket for front of frame

  4. Build middle vertical column, front, use 2 brackets.
    • Build middle vertical column, front, use 2 brackets.

  5. Build middle rear vertical column. Build middle rear vertical column.
    • Build middle rear vertical column.

  6. Build rear 3rd corner vertical. Use 2 double and one single bracket. (note later time)
    • Build rear 3rd corner vertical. Use 2 double and one single bracket. (note later time)

  7. Build 4th rear corner vertical. (second pix at same time as last)
    • Build 4th rear corner vertical. (second pix at same time as last)

  8. Build rear corner horizontal using a single bracket.
    • Build rear corner horizontal using a single bracket.

  9. Do the same on the rear left corner.
    • Do the same on the rear left corner.

  10. Install rear vertical of overall frame
    • Install rear vertical of overall frame

  11. Install single bracket for rear left vertical, and rear right vertical. Install single bracket for rear left vertical, and rear right vertical.
    • Install single bracket for rear left vertical, and rear right vertical.

  12. nstall single bracket on right front cutting chamber horizontals. nstall single bracket on right front cutting chamber horizontals.
    • nstall single bracket on right front cutting chamber horizontals.

  13. Install middle black supports on the floor of the frame, using single black brackets, 1 per meeting point Install middle black supports on the floor of the frame, using single black brackets, 1 per meeting point
    • Install middle black supports on the floor of the frame, using single black brackets, 1 per meeting point

  14. Install 3 short 2040 extrusions on the rear base of the frame.
    • Install 3 short 2040 extrusions on the rear base of the frame.

  15. Tighten down all joints. Insert spring nuts as needed.
    • Tighten down all joints. Insert spring nuts as needed.

  16. Inner distance between extrusions for the front compartment should be 86 cm.
    • Inner distance between extrusions for the front compartment should be 86 cm.

    • Space between front horizontal and mid horizontal should be 41 cm on the inside.

    • Use the small polycarbonate separation panel - mark a .6x.6 cm corner cut out.

    • Cut the corner out with a dremel tool. The corner cutout allows the panel to fit against the walls of the frame.

    • Do the same for the second of the same panel.

    • Peel the protective covering from the small panel, and insert.

    • Peel the protective covering from the long panel, and insert.

    • Take out the panels, insert the table frame.

    • Insert the small separation panels

    • Insert the large separation panels

    • Measure for parallel of the front and back. Also measure the diagonals to check that they are within 2 mm.

    • Mount the base brackets of table to the outer frame - both for the front and back side of the table.

    • Mount the middle rear vertical to the outer frame.

    • Place the gantry frame on top of the table.

    • Cut out the upper corner of the small separation panel, for both panels.

    • Place the separation penels in the frame.

    • Measure the diagonal of the gantry frame to see that it's square.

    • Tighten down the gantry frame to the bottom outer frame. Start with the 4 corners.

    • Then tighten down the 3 more single brackets in the front and in the rear.

    • Cut rubber gasket to size for the long separator windows - 2 seams on top and bottom horizontals. See example of how the rubber gasket fits in the grooves of the aluminum extrusion.

    • Insert rubber gasket in the bottom window edge. Poke in with the blunt end of a pen or some other object that helps the rubber to be pushed in the groove to create a tight seal.

    • Insert rubber gasket in the top window edge.

    • Insert small vertical support, a 4080 extrusion - rear post for the door.

    • Start with the spring nuts

    • Put in bracket and 2 screws.

    • Put in 2 remaining screws. Repeat for the second vertical support.

    • Continue to the 4040 extrusion for the front post of the door.

Robert Kirk